The TAPAC mural project: Progress Report

25th April 2007: The boom lift stalled again after heavy rain cleared … so we worked the lower parts. We learn to reserve the lower parts when the crane breaks down. Mostly caused by the site supervisor’s failure to top-up the diesel as required.
PIMP MY MASK: Activitieswhen work on the TAPAC mural is disrupted. There were many disruptions. Global warming is really showing, it rained a lot in April when it should not and its extremely hot when its sunny. The boom-lift crane breaks down rather often and it take days for their mechanic to appear.
 